CCUS projects in Europe
EU
21
CO2 storage projects
9
countries with CO2 storage projects
26
MT CO2/Year CO2 capacity injection by 2030
Europe
24
CO2 storage projects
3
countries with CO2 storage projects
66
MT CO2/Year CO2 capacity injection by 2030
Name
Country
Elements of the CCS Value Chain covered
Status
Planned start of operations date
Capacity at start date (Mtpa)
CO2 capacity after completion
CO2 EOR Project Croatia
79
CaptureStorageTransport
In operation
The injection of CO2 in Ivanić oilfield started in October 2014 and northern part of Žutica oilfields in October 2015.
0
N/A
Stenlille demo CO2-storage
81
Storage
Advanced Development
2025
0.5
cO2 Capacity after full expansion (Mtpa)
Go4ECOPlanet
89
Capture
In planning
The vision for Go4ECOPlanet is to create a net-zero plant by 2027.
0
H2GE Rostock
83
Capture
In planning
Production might begin in 2029 if a FID is reached in 2025 or 2026 for the roughly one billion euro investment project. The unresolved difficulties will be clarified through a feasibility study.
2
2
SHARC
96
Capture
Early Development
The final investment decision is expected to be made in 2023, with planned start in 2025/26.
0.4
0.4
Poland – EU CCS Interconnector
89
Transport
In planning
Start-up of first facilities is planned in 2025 – 2026
2.7
8.7
H-Vision
87
Capture
Early Development
H-vision provides for the construction of two hydrogen plants: Plant 1 in 2027 (750 megawatts of low-carbon hydrogen) Plant 2 in 2032 (1,500 megawatts of low-carbon hydrogen).
1.3
2.7
Twence CO2 capture plant
87
Capture
Advanced Development
The plant is expected to start operating in the last quarter of 2023.
0.1
0.1
Longship (includes Northern Lights 1)
88
CaptureStorageTransport
Advanced Development
2024
1.5
Expansion through Northern Lights 2 project
DMX Demonstration in Dunkirk (“3D” project)
82
Capture
Advanced Development
2025 full-scale CCS plant of 1 Mtpa - 10 Mtpa by 2035
1
10
Pycasso – PYrenean Carbon Abolition through Sustainable Sequestration Operations
82
StorageTransport
In planning
2030
1
5.9
H2morrow
83
Capture
Early Development
The full value chain of the project could be put into operation by 2027 the earliest and 2030 the latest.
1.9
1.9
Leilac 2
83
Capture
Advanced Development
The demontration plant aims to become operational by 2025.
0.1
0.1
Steelanol
78
Capture
In operation
8 DEC 2022 - ArcelorMittal inaugurates flagship carbon capture and utilisation project at its steel plant in Ghent.
0.125
N/A
Greensand
81
StorageTransport
In operation
If successful, the pilot would lead to full-scale CO2 storage in the Nini West field by 2025
1.5
8